banner project

The Baltica 2 offshore wind farm project is located in the Southern part of the Baltic Sea, approximately 40 kilometres off the Polish coast and scheduled for commissioning by end of 2027. The offshore wind farm will have a capacity of approximately 1.5 GW and will be Poland’s largest-ever renewable energy project with 107 wind turbines producing enough green energy to cover the power consumption of approximately 2.4 million Polish households.

Client: PGE Group and Ørsted

Partner: Consortium Partner: Semco Maritime

Location: Poland

Workscope: Main EPCC Contractor (Detailed Engineering, Procurement, Construction, Offshore Commissioning) for 4 offshore substation platforms and module support frames

Duration: Q2.2023 – Q4.2027 (scheduled)

Main facilities:

  • 04 OSS Topsides
  • 04 MSFs